Green Schoolyards From Award-Winning Grant Program

Earlier this year, the San Francisco Public Utilities Commission (SFPUC) celebrated the one-year anniversary since the launch of its Green Infrastructure (GI) Grant Program, the City’s first large-scale GI grant program that provides funding to San Francisco property owners to capture and manage stormwater through GI. The first year of the GI Grant program saw many milestones, including an applicant workshop with over 100 participants, 6 project grants totaling $5M in funding, and winning a 2020 Outstanding Sustainable Stormwater Program Award from the California Stormwater Quality Association (CASQA).

Today, we celebrate another exciting milestone - the first two grant projects have completed construction, just in time for the rainy season!

 
 

Bessie Carmichael Middle School

The SFPUC awarded San Francisco Unified School District (SFUSD) $0.4M, working with SFUSD’s Green Schoolyards program and additional funding, to transform the Bessie Carmichael schoolyard. The GI Grant Program funded:

  • Site soil remediation

  • A repaved and painted play yard

  • A mural to promote education around the environment and infrastructure through art

  • Three in-ground planted bioretention basins, and

  • Four above grade planters to manage roof and yard stormwater runoff.

Altogether these seven stormwater management BMPs will manage 275,000 gallons of stormwater annually within the Channel Watershed.


 

Lafayette Elementary School

An additional $0.5M was awarded to fund stormwater infrastructure improvements at Lafayette Elementary School, integrated into SFUSD’s building modernization project. The grant funded:

  • Two bioretention basins

  • A large planted dry creek bed to manage stormwater runoff from the play yard and a portion of the roof

  • New planters

  • Impervious surface removal, and

  • Educational signage throughout the yard.

The stormwater improvements will manage 350,000 gallons of stormwater annually in the Sunset Watershed.

Lotus Water continues to provide technical and programmatic support for the GI Grant Program, working closely with the SFPUC to develop the program guidebook, perform site visits at potential grant project sites, review applications and plan submissions, and provide construction administration services.  

Read more about the GI Grant Program here.

New GI Grant Program is a HIT!

gigrant_blog.JPG

The SFPUC GI Grant Program has launched!  Lotus helped developed the program and will be providing ongoing technical support during implementation.  The first public workshop about the program sold out with over 100 attendees, and the first applicant has already submitted!  The SFPUC aims to award $6M in GI grants during the first two years of the program, with up to $2M max per project. Learn more about the program and how a grant could benefit you!

Award for Holloway Green Street

The EPA recently awarded the Holloway Avenue Green Street Project with an Honorable Mention as part of its 2018 Performance and Innovation in the State Revolving Fund Creating Environmental Success (PISCES) program. The project (also referred to as the Lake Merced Green Infrastructure project) is located within the Ingleside Neighborhood and is one of eight SFPUC Early Implementation Projects that have been constructed or are currently being constructed as part of Sewer System Improvement Program. Completed in 2017, the project converts a nine-block stretch of an urban residential street and important bike route into a high-performing green street that also provides pedestrian and bike safety improvements. Parking lanes were reconstructed with pervious concrete pavement to manage roadway runoff and bioretention was incorporated into new corner bulbouts and sidewalk planters to manage sidewalk runoff while also adding greenery along the corridor. The new green infrastructure measures will remove approximately 1 million gallons of stormwater each year from the City’s combined sewer system.

Lotus Water led the planning, stormwater modeling and preliminary design of this project. Additionally, we are providing post-construction performance monitoring and analysis and performing maintenance inspections.

Read more about the PISCES award here!